Richard J. Conway and Justin A. Chiarodo
The defendant was a joint venture that had entered into a fixed price indefinite delivery/indefinite quantity (ID/IQ) contract with the government to provide architect and engineering services for an Everglades restoration project overseen by the Army Corps of Engineers. As the project was a first-of-its-kind effort, the Corps planned to reduce its cost risk by using a fixed-price contract performed through task orders. The ID/IQ contract provided negotiated fixed-price labor rates and a negotiated profit component, derived primarily from past Corps contract experience. Subsequent fixed-price task orders were lump-sum, determined in accordance with the agreed-upon labor rates multiplied by the number of days required to complete the work, and included the agreed-upon profit component. The joint venture saw its profit margin increase through the use of efficient staffing of task orders with lower-cost resources than those contemplated in the original ID/IQ formulas. Continue reading “Increased Profit Under a Firm-Fixed Price Contract a False Claim? Not So Says One Federal District Court”