In The Boeing Company v. United States, 2019-2148 (Aug. 10, 2020), the Federal Circuit rejected the government’s argument that Boeing’s claim—which was based on an apparent conflict between (1) a statutory provision limiting the costs the government may recover for cost accounting practice changes to the aggregate increased cost to the government, and (2) a FAR provision under which the government’s recovery considers only the changes that increase costs to the government, and disregards changes that decrease costs to the government—was waived because Boeing did not raise the issue prior to contract award. Continue reading “Government Reliance on Waiver Argument to Keep Price Adjustment Windfall Fails”
Category: Cost Accounting and Pricing
Recovering COVID-19 Costs Where Section 3610 of the CARES Act Does Not Apply
Below we provide a brief refresher of key considerations for contractors considering COVID-related REAs or claims. Of course, the particular facts and terms of each contract will ultimately determine whether cost increases are recoverable.
What Types of Costs May Be Recovered?
Costs stemming from COVID-19 may be recoverable under several Federal Acquisition Regulation (“FAR”) clauses:
- The Changes Clause (g., FAR 52.243-1): A wide array of costs may fall under the Changes clause, such as costs stemming from government direction to alter or stagger work hours, provide additional personnel, use more costly procedures, use procedures requiring additional training for personnel, provide personal protective equipment, or perform additional cleanings. A recent Department of Defense Memorandum is instructive as to how such costs are likely to be viewed, advising that contracting officers should consider whether such costs are “reasonable to protect the health and safety of contract employees as part of the performance of the contract.”
- The Stop Work Order Clause (FAR 52.242-15): Costs stemming from the government’s direction to stop work will generally be recoverable under this clause. As discussed in our previous blog post, this may include the cost of “idle time” where employees are unable to access work sites, potentially providing some relief to contractors who are not covered by Section 3610 of the CARES Act. Arguably, this clause should cover situations in which employees cannot work due to government-required quarantine procedures or government-caused delays, even if the work site is technically open—though this remains an open issue.
- The Government Delay of Work Clause (FAR 52.242-17): Where the government causes a delay, the costs stemming from such a delay, such as increased material costs, may be recoverable under this clause.
Notably, while the Excusable Delays clause (e.g., FAR 52.249-14) excuses a contractor’s failure to perform for reasons including “epidemics” and “quarantine restrictions,” this clause does not provide financial relief, but rather, provides a basis for excusing what might otherwise give rise to a termination for default.
What Is the Difference between an Equitable Adjustment and a Claim?
A claim is a formal written demand subject to the detailed procedures set forth in the Contract Disputes Act (“CDA”). Once a claim is made, the Contracting Officer must issue a final decision within 60 days (or, for claims over $100,000, provide a firm date by which a final decision will be issued), which may be appealed to the Boards of Contract Appeals or the Court of Federal Claims. Claims must include a “sum certain”—i.e., the amount of damages being claimed—and claims of $100,000 or more must be certified by the contractor as current and accurate.
An REA is generally considered less adversarial than a claim and is not subject to a formal disputes process. There is no set timeline for resolution of an REA; however, if an REA is not resolved satisfactorily, it can be converted into a claim.
In the context of COVID-related costs, there are advantages and disadvantages of both options. The less formal REA process provides agencies more leeway as they work to coordinate internally on how to address costs relating to COVID-19, which may ultimately be to the benefit of contractors. However, the claims process puts the government “on the clock” and, thus, may result in a faster response. Note that contractors are entitled to interest that accrues while a claim is pending, but not while an REA is pending. As for legal costs, they are allowable when incurred to support an REA, but are unallowable when incurred in support of a claim.
Timing Considerations
Whether a contractor ultimately submits a request for equitable adjustment or claim, it must notify its Contracting Officer of the delay, disruption, or right to an adjustment, with different deadlines depending upon which clause applies. For example:
- FAR 52.242-15 (Stop Work Order Clause) requires contractors to assert their right to an adjustment within 30 days after the end of the period of work stoppage;
- FAR 52.242-17 (Government Delay of Work) requires contractors to notify the Contracting Officer within 20 days of the act or failure to act giving rise to the delay; the contractor must also assert the amount of the claim in writing as soon as practicable after the termination of the delay or interruption, but not later than the day of final payment under the contract; and,
- FAR 52.243-1 (Changes) requires the contractor to assert its right to an adjustment within 30 days from the date of receipt of a written change order. There is an exception “if the Contracting Officer decides that the facts justify it,” where the request is made before final payment of the contract.
Claims are also subject to a six-year statute of limitations.
As COVID-19 issues permeate virtually all aspects of commerce nationally and internationally, we stand ready to help. Blank Rome’s Coronavirus (“COVID-19”) Task Force includes interdisciplinary resources across every business sector.
Federal Circuit Maintains That Contractors Must Read between the Lines to Determine Expressly Unallowable Costs
Scott Arnold and Carolyn Cody-Jones
Renewed Focus on Contractor Business System Reviews
Certified Cost and Pricing Data Thresholds to Increase July 1, 2018
Scott Arnold and Sara N. Gerber
Government Contractor Shutdown Advisory
Justin A. Chiarodo and Albert B. Krachman
With yet another government shutdown looming, contractors face a number of uncertainties and challenges that warrant close attention—regardless of whether a shutdown takes place or how long it lasts. Among other challenges, contractors may face a lack of incremental funding; the inability to enter into new contracts or contract modifications; closed government facilities; furloughed government employees; delayed payments; increased indirect costs; and unexercised and deferred contract options. Below we offer six suggestions to help address key areas impacted by a shutdown, including contract funding, internal and external communications, recordkeeping, and deadlines.
New Year’s Resolutions: Top 5 Consequential Changes in the 2018 NDAA
Adam Proujansky and Ioana Cristei
The National Defense Authorization Act (“NDAA”) for Fiscal Year 2018 was signed into law on December 12, 2017, and authorizes a topline national defense budget of $700 billion. While the 2018 NDAA makes a number of changes to Department of Defense (“DOD”) policy and programs, in this article we explain five major changes to acquisition policy and how they will impact the way companies do business with DOD. Continue reading “New Year’s Resolutions: Top 5 Consequential Changes in the 2018 NDAA”
ASBCA Grants $253 Million Northrop Post-Retirement Benefits Claim
David Yang
GSA’s Transactional Data Reporting Rule Ushers in a New Era
Merle M. DeLancey Jr. , Justin Chiarodo, and Philip Beshara
Last month, the General Services Administration (“GSA”) finalized a rule marking what the agency describes as the most significant development to its Schedules program in over two decades. The rule completely changes how GSA will analyze vendor pricing for products and services.
Under the rule, vendors will eventually be required to submit monthly transactional data reports with information related to orders and prices under certain GSA Schedule contracts and other vehicles. Along with the implementation of the new Transactional Data Reporting (“TDR”) requirement, GSA will relieve vendors from two preexisting compliance burdens—eliminating the Commercial Sales Practices (“CSP”) and Price Reductions Clause (“PRC”) reporting requirements when vendors begin submitting transactional data.
While vendors should welcome the relief provided from the elimination of two burdensome regulations, the shift to TDR will not be without cost and risk; and, the eventual efficiencies promised by GSA remain to be seen. Indeed, the impact of the change will likely extend beyond compliance burdens, with potential effects varying from the nature of False Claims Act suits to the potential publication of competitive information.
We summarize these and other key takeaways from the new rule below, and answer questions important to vendors as GSA rolls out this significant development. Continue reading “GSA’s Transactional Data Reporting Rule Ushers in a New Era”