60-Second Sustains: Life Science Logistics, LLC

Elizabeth N. Jochum

Life Science Logistics, LLC
B-421018.2, .3

  • The protester alleged that GSA failed to conduct meaningful discussions by not raising, in pre-corrective action discussions, significant weaknesses that resulted in the proposal being rated unacceptable in a post-corrective action evaluation.
  • GAO has held that, when an agency seeks revised proposals and performs a new evaluation, that reevaluation may identify flaws in a materially unchanged proposal that the agency would have been required to discuss with the offeror, had the flaws been identified when the proposal was initially evaluated.
  • In that situation, the agency must reopen discussions in order to disclose its concerns.
  • GSA argued Life Science’s pre- and post-corrective action proposals were materially different, but GAO found that the content that gave rise to the significant weaknesses was present in both proposals but had been overlooked in the initial evaluation.
  • Since the Agency did not advise Life Science of the significant weaknesses in its initial proposal when conducting discussions, GAO sustained the protest and recommended GSA reopen the procurement, conduct meaningful discussions, and evaluate revised proposals.

Surviving Proposal Weaknesses after Discussions: What Not to Do

Albert B. Krachman

With apologies to Paul Simon, this is another in a series of articles on the 50 ways contractors can lose awards on federal contracts. These cautionary tales should inform anyone in a contractor organization with responsibility for authorizing, preparing, or negotiating competitive federal contract proposals.

Like the inverse of Steven Covey’s Seven Habits of Highly Effective People bestseller, the mistakes that lead to lost awards are well known and include: carelessness, greed, lack of attention to detail, procrastination, and cursory (or omitted) red-team reviews. This article highlights another surefire path to disaster: failing to adequately correct proposal weaknesses after discussions.

This lesson arises out of a clash between BNA and Lexis, legal search titans, over a U.S. Treasury contract. The combatants were seeking award of a contract for electronic research services for IRS staff, described in a GAO Bid Protest decision, LexisNexis, a Division of RELX Inc., B-418885; B-418885.2 (October 8, 2020).

Treasury’s solicitation required that offerors both describe their search solutions in technical proposals, and have a working computing solution, active for government testing. After initial proposal submissions and initial evaluations, the government advised offerors of weaknesses and deficiencies in their proposals and in their computing solutions. Treasury advised Lexis that its proposal suffered from a significant weakness due to Lexis’ computing solution’s return of erroneous search results. Discussions were opened and offerors were permitted to submit final proposal revisions. Offerors were also permitted to correct any deficiencies in their computing solutions before another round of government testing.

Continue reading “Surviving Proposal Weaknesses after Discussions: What Not to Do”