Stephanie M. Harden and David L. Bodner ●


Welcome to our new “Lifecycle of a Claim” series. This series will explore the Contract Disputes Act claims process, with practical guidance stemming from recent case law every step of the way. Click the subscribe button on the right to get timely updates right in your inbox!
The claims landscape for government contractors can be a minefield of both procedural and substantive issues. Through this series, we are providing a guide to one common type of claim: those arising out of a “change” to the contract.
We are pleased to introduce this infographic (click here or the image below to expand), which illustrates the lifecycle of a typical claim:
This post focuses on Steps 1 and 2 of this process: identifying when a change has occurred and providing timely notice to the Contracting Officer. We begin with a few foundational questions:
What is a change?
There are two primary types of changes:
-
-
- Actual Changes: According to the Federal Acquisition Regulation (“FAR”), a change occurs when the Contracting Officer issues a written order to make changes within the general scope of the contract to matters such as drawings, designs, or specifications; the method of shipment or packing; or the place of delivery. See, e.g., FAR 52.243-1.
- Constructive Changes: A constructive change arises when the contractor is required to perform work beyond the contract requirements, but the Government does not issue a formal change order. Constructive changes can arise from informal orders, defective specifications or other misrepresentations, interference from the Government, or constructive accelerations of performance.
-